angelburst29
The Living Force
Nearly half of the newly constructed Genoa bridge is done, with a deadline set for the bridge to be completed before Summer 2020.
Engineers working around the clock to complete Genoa bridge by summer
FILE PHOTO: General view of the partially completed new Genoa bridge, also known as the Polcevera viaduct, in Genoa, Italy, February 5, 2020. REUTERS/Yara Nardi
February 10, 2020 - Day and night for months on end hundreds of workers have been toiling with cranes, pipes, concrete blocks and steel rods to complete a new bridge in the northern Italian port city of Genoa by a summer deadline.
Forty three people were killed on Aug. 14, 2018, when the old bridge collapsed, hurling cars and trucks to the ground below and prompting national outrage, especially against infrastructure group Atlantia which had operated it.
Completing the new infrastructure in a timely fashion is key to re-establishing the connection between Genoa and France.
Bridge Collapses in Italy, Burying a Crossing Truck
It looks quite serious:
Engineers working around the clock to complete Genoa bridge by summer
FILE PHOTO: General view of the partially completed new Genoa bridge, also known as the Polcevera viaduct, in Genoa, Italy, February 5, 2020. REUTERS/Yara Nardi
February 10, 2020 - Day and night for months on end hundreds of workers have been toiling with cranes, pipes, concrete blocks and steel rods to complete a new bridge in the northern Italian port city of Genoa by a summer deadline.
Forty three people were killed on Aug. 14, 2018, when the old bridge collapsed, hurling cars and trucks to the ground below and prompting national outrage, especially against infrastructure group Atlantia which had operated it.
Completing the new infrastructure in a timely fashion is key to re-establishing the connection between Genoa and France.
A joint venture comprising Salini Impregilo and shipbuilder Fincantieri is responsible for the project, which will cost 202 million euros, excluding the amount needed for the demolition of the old viaduct.
Work has now gone past the halfway mark, with 16 of the 18 planned 40 metre-high (131 feet) columns in place and seven out of 19 deck sections laid.
“The bridge is set to be completed before summer 2020 so we are making every possible effort to meet this deadline,” site construction manager Stefano Mosconi said.
Some 70,000 cubic meters (2472 cubic feet) of concrete have been used in the construction of the viaduct, which stretches about 1 kilometer across the valley. Much of the work is invisible, with the column foundations sunk 50 meters (164 feet) underground.
Security and durability have been central to the project, but so have environmental aspects. In energy terms, the bridge will be self-sufficient, with solar panels providing electricity for the lighting system.
“We are convinced that this can mark the beginning of a turning point for our sector, a turning point for the country,” Meistro said.
Bridge Collapses in Italy, Burying a Crossing Truck
The incident occurred on Wednesday near Albiano in Massa Carrara province in Tuscany at a bridge connecting the provincial roads SP62 and SP70. A vehicle was crossing the bridge at the moment of the collapse.
It looks quite serious: